The city has provided us with the following update regarding the 14th street bridge construction that I am sure you have noticed recently.
They are currently completing some finishing touches on the bridge and planning intersection paving work for September.
Work to be Completed
- The east intersection is scheduled to be paved on September 8. This work will be performed overnight, and the bridge will be closed to traffic from 9:00 p.m. to 5:00 a.m. the following morning.
- Work at the west intersection is still in the planning stage. During construction, they identified a potential need for subgrade repairs before the final pavement can be placed. As a result, an additional closure will likely be required for the west intersection work. However, the timing and duration of that closure have not yet been determined.
- They will be completing deck grooving activities on the north half of the bridge from September 10 to 14. Deck grooving on the south half of the bridge is scheduled for September 16 to 18. Throughout the deck grooving work, continuous eastbound traffic will be maintained. The work zone will simply shift from the north side to the south side of the bridge on September 15 to facilitate the second phase of the work
This information will also be posted on the project website within the next few days.